Successful audit at the Schwandorf site
Zu allen NeuigkeitenFor nearly 30 years, we have supported the Zweckverband Müllverwertung Schwandorf (ZMS) in the maintenance and overhaul of its waste-to-energy plant, which includes four furnace lines.
Electricity, steam, and heat generated by the facility supply industry, public networks, and the district heating system.
This year, the overhaul of furnace line 1 was successfully completed, including work on the boiler pressure section, flue gas cleaning system, SCR unit, and auxiliary systems. Up to 30 employees were on duty around the clock. All activities were carried out in a safe manner and finished on schedule.
Thanks to the to the project management and site leadership, this milestone became reality.
The next overhaul is already on the horizon: from mid-July to mid-August, furnace line 4 will undergo extensive measures.
Safety, quality, and adherence to deadlines remain our highest priorities.
We thank our customer for their long-standing trust and consistently goal-oriented collaboration.